Project Progress

Overall Project Progress = 65% as of December 31, 2017

  • Mobilization - 85% out of 100%

  •  Design - 87% out of 100%

  •  Earth work - 60,000,000m3 out of 97,000,000m3

  •  Bridge works - 45 bridges out of 65 bridges

  •  Tunnel works - 8 tunnels  out of 12 tunnels

  •  Culverts(drainage) - 28 km out of 31 km

  • Track works (Sleeper production ,Rail transportation and track laying) -68% out of 100%

  •  Station building - 5 station out of 10 stations

  • Power Traction substation - 6 traction substation out of 8 traction substations

  • Technical building 6 technical building out of 10 technical buildings

  •  Radio tower - 8 radio tower out of 12 radio tower

  • Workshop(depots) building - 90% out of 100%

  • Geotechnical investigation - 98%  out of 100%

 To view the detailed project status download  the pdf presentation.

 

 

 